TEMPUS Joint European Project 14461-1999

"NEW EDUCATIONAL TOOLS"

Tempus Joint European Project









ANNEX II/5
CONTRACT No : UM_JEP-14461-1999






Revised Budget and Activity Plan




























WORKPLAN for 2st project year

TO DATE PLANNED FOR REMAINDER OF YEAR














Outputs/Activities* Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
1. Needs and models identified





o




1.1. Study visits to EU partner universities x=xxx


====






1.2. Reporting on EU models and PL needs xxxx



xxxx





2. New SMIS designed and introduced










o
2.1. Design, consultation and approval of a model of the SMIS











2.2. Development of IT support system xxxx xxxx xxxx xxxx xxxx xxxx xxxx xxxx xxxx xxxx xxxx xxxx
2.3. Selection and purchase of equipment

x x x x x




2.4. Development of a concept for database protection x x x x







2.5. Implementation of SMIS xxxx xxxx xxxx xxxx xxxx xxxx xxxx xxxx xxxx xxxx xxxx xxxx
2.6. Modernisation of administrative structures


xxxx xxxx xxxx xxxx xxxx xxxx xxxx xxxx xxxx
3. CSA procedure designed and introduced






o



3.1. Development of software and manuals


xxxx







3.2. Implementation of new admission procedure


xxxx xxxx xxxx xxxx xxxx



4. VEIN set up










o
4.1. Designing a concept and a standard format for catalogues


x x






4.2. Designing an IT platform for the transmission of data











4.3. Implementation of designed models xxxx xxxx xxxx xxxx xxxx xxxx xxxx xxxx xxxx xxxx xxxx xxxx
4.4. Feasibility study for setting up a national data base xxxx xxxx xxxx xxxx ==== xxxx xxxx xxxx xxxx xxxx xxxx xxxx
5. A plan for further action developed










o
5.1. Designing an integrated general MIS xxxx xxxx xxxx xxxx ==== xxxx xxxx xxxx xxxx xxxx xxxx xxxx
5.2. Preparation of expert studies on individual modules











5.3. Seminar on collaborative actions in the area of MIS





x




6. A model for flexible study systems developed










o
6.1. Preparation of case studies of EU and Polish models xxxx xxxx xxxx xxxx ==== xxxx
xxxx xxxx


6.2. Conference on flexible study systems
x



x




7. Efficient project management ensured










o
7.1. Day-to-day management of the project xxxx xxxx xxxx xxxx xxxx xxxx xxxx xxxx xxxx xxxx xxxx xxxx
7.2. Management meetings and monitoring

x x

x

x
x










































* Please use the same headings as in the Original Application and indicate in bold the new/modified ones


























Deadline for achievement of output: o Activities carried out in the partner country: x Activities carried out in the EU: =